5th Unit C&I System | |||
Steam Generator | |||
SL. No. | System | Work Done | Work Pending |
1. | Oil Elevation | AB & CD:- Ready | EF:- i) Spark rod(2 no’s)required materials shortage). |
2. | Mill group | A, B, C, D: - Ready(Most of the important signals are made through. few parameters monitoring still pending.) | E: - Under progress. F:-Feeder calibration and other are pending.All Mill-Vibration Monitoring System |
3. | Fuel oil System | LOTV & Oil Flow Controller are ready | LORV are not ready(materials shortage) |
4. | Seal air system | Fans & Emergency damper are ready | - |
5. | SADC System | Erection part is over | 4nos. I/P Converter shortage |
6. | Burner tilt | Erection completed | - |
7. | ID fan | Fan A & B are ready(Most of the important signals are made through & Auto operation of Furnace Draft has been performed) | Vibration Monitoring System |
8. | FD fan | Fan A & B are ready (Most of the important signals are made through) | Vibration Monitoring System |
9. | PA fan | Fan B are ready (Most of the important signals are made through) | Fan A work under process.Vibration Monitoring System. |
10. | Air Pre-heater | A & B are ready (Most of the important signals are made through) | No motion signal |
11. | O2 monitoring system | Ready | - |
12. | HP Bypass System | Field jobs have been over. Loop tuning has been done. | Final performance. |
Turbo-Generator System | |||
SL. No. | System | Work Done | Work Pending |
1. | Bring & Jacking Oil System | Remote operation of EOP AC & DC, JOP 1 &2, Temperature Controller. | Sub Group Control |
2. | Governing System | partly commissioned | Control valve F/B, ATT, Fire protection etc. |
3. | Vacuum breaker | - | Not commissioned |
4. | Synchronizer | - | Not commissioned |
5. | Seal Oil System | Remote operation of AC SOP 1 & 2 and DC SOP | - |
6. | H2 purity monitoring system | local panel is ready | Proper remote interface is pending |
7. | Turbine Drain valves & Ext. NRV | Around 50% is ready | - |
8. | Evacuation System | Partly ready for operation | Sub Group Control |
9. | LP Bypass System | Ready for operation & final tuning has been done. | - |
10. | PRDS System | Pr control loop is ready.HT- temperature control is in auto mode. | LT-temperature control yet to be done |
11. | Gland Seal System | Erection of instruments & control valves | Performance Observation & Final tuning pending |
12. | BFP | A,B,c:- Important parameters have been made through | C:- Remote operation.All BFP-Vibration Monitoring System |
13. | CEP Pump | Ready for operation | Vibration Monitoring System |
14. | DMCW System | Important part has been completed ( Pump stand by operation & auto loop operation of boiler recirculation valve ) | Few parameter display is pending & auto loop operation of Turbine recirculation valve. |
15. | ACW and CWP System | CWP A,B&C, ACW A Switchgear to DCS Interface has been done and most of the vital signal has been made ready | DCS interface is pending. |
16. | CT Fan | MCC to DCS interface has been done | Interconnection of bration & Oil level monitoring system. |
Common items | |||
SL. No. | System | Work Done | Work Pending |
1. | UPS | Major work has been done | Battery healthiness monitoring system |
2. | Unit Control Panel | Major work has been done | Observation of Performance of the system( EF –Elevation interface ) |
3. | Hardwire annunciation system | Major work has been done | Observation of Performance of the system |
4. | CCTV | Work started | - |
5. | LVS | Client Software has been changed and the system has been made ready | Observation of final Performance. |
6. | HART management system | System commissioned | - |
7. | Acoustic Steam leakage detection system | Field mounting of sensor has been done | Remote interface |
8. | Remote Operation of Electrical System (Incoming BKR, Tie BKR etc.) | Very few cable has been terminated 6.6 Kv Supply 1 & 2 to CHP- BKR &ST#3 to DCS interface has been done logic checking is pending. | DCS interface is pending |
9. | ASH Handling System | Bottom Ashing, Ash slurry Pump House, Fly Ash & Vaccum Pump House, Silo – UPS, PLC & Control Panel Erected. | No Interfacing of the system to PLC & Control Desk has been Started. Some Transmitters & Gauges are connected in unapproachable place. |
10. | DM PLANT | Only two nos. Turbine Flow meters has been erected, very few nos. of limit switches has been connected on the actuators. | PLC Panels & Control Desk has not erected. |
Search
Latest topics
Updated Status of Unit 5 C & I as on 17/11/2008
Admin- Admin
- Posts : 3
Join date : 2008-08-30
|
|
25th June 2013, 13:34 by rajena
» Progress Report of Unit No. 6 for the month of May 2009
19th June 2009, 14:15 by mbdcl
» Progress/Program of M/s. BHEL for Major Balance Activities.
27th April 2009, 14:35 by mbdcl
» Unit No.5 : Status of Pending BOP work.
27th April 2009, 14:15 by mbdcl
» Unit No.5 : Status of Pending BOP work.
27th April 2009, 14:14 by mbdcl
» Updated Status of Balance work on Main Plant package
13th March 2009, 18:00 by mbdcl
» Updated Status of Unit-5 Balance Work for BOP Package
12th March 2009, 19:12 by mbdcl
» Status Report of Unit No.6 Construction as on 12.03.09.
12th March 2009, 14:48 by mbdcl
» [b]Progress of Unit No.5 BOP Construction as on date 20.02.09.[/b]
9th February 2009, 18:03 by mbdcl