Updated Status of Unit-5 Balance Work for BOP Package Empty25th June 2013, 13:34 by rajena

» Progress Report of Unit No. 6 for the month of May 2009
Updated Status of Unit-5 Balance Work for BOP Package Empty19th June 2009, 14:15 by mbdcl

» Progress/Program of M/s. BHEL for Major Balance Activities.
Updated Status of Unit-5 Balance Work for BOP Package Empty27th April 2009, 14:35 by mbdcl

» Unit No.5 : Status of Pending BOP work.
Updated Status of Unit-5 Balance Work for BOP Package Empty27th April 2009, 14:15 by mbdcl

» Unit No.5 : Status of Pending BOP work.
Updated Status of Unit-5 Balance Work for BOP Package Empty27th April 2009, 14:14 by mbdcl

» Updated Status of Balance work on Main Plant package
Updated Status of Unit-5 Balance Work for BOP Package Empty13th March 2009, 18:00 by mbdcl

» Updated Status of Unit-5 Balance Work for BOP Package
Updated Status of Unit-5 Balance Work for BOP Package Empty12th March 2009, 19:12 by mbdcl

» Status Report of Unit No.6 Construction as on 12.03.09.
Updated Status of Unit-5 Balance Work for BOP Package Empty12th March 2009, 14:48 by mbdcl

» [b]Progress of Unit No.5 BOP Construction as on date 20.02.09.[/b]
Updated Status of Unit-5 Balance Work for BOP Package Empty9th February 2009, 18:03 by mbdcl


    Updated Status of Unit-5 Balance Work for BOP Package

    avatar
    mbdcl


    Posts : 9
    Join date : 2009-02-04

    Updated Status of Unit-5 Balance Work for BOP Package Empty Updated Status of Unit-5 Balance Work for BOP Package

    Post  mbdcl 12th March 2009, 19:12

    Preface : Unit-5 was under operation at part load.



    1. Raw Water Reservoirs : Completed long back.

    2. Raw Water Pump House:

    Pump House & Electrical Bldg :

    · Major Civil & Electro-mechanical work completed.

    · RW Pumps and Ash Water Make Up Pumps commissioned.

    · Erection of 5 Ton Cap EOT pending.


    3. Pre-Treatment Plant:

    · Clarifloculators-A : Tank-A is ready and under operation.

    · Clarifloculators-B : Civil work completed. Mechanical installation is in progress.

    · Cascade Aerator : Foundations complete. Work for Super-structure is in progress.

    · Stilling Chamber : Complete.

    · Flash Mixer (A & B): Complete.

    · Clarified Water Channels: Completed except for Filter House.

    · Filter House : Foundations complete. RCC work for Pipe Gallery & Filter bed in slow progress. Cover slab for Pipe Gallery portion cast.

    · Chemical House & MCC Room : Civil work above Plinth level is in progress including brick work. Roof for MCC Room cast.

    · Filtered Water Pump house : Reinforcement for Base Raft is in progress. For Sump portion, base raft is already cast. Slow progress.

    · B/W Collection Tank & Sludge Sump : RCC work for B/W Collection Tank & Pump House major achieved. Civil work for Sludge Sump & Pump house in progress.


    4. Clarified Water Reservoirs & Pump House:

    Water Reservoirs & Pump House :

    · Major RCC work complete with installation of Sluice gates.

    · Formwork for pending Maint Bay Roof & staircases are in progress.

    · Brickwork/plaster major completed.

    · Installation of MCC panels completed and charged at one Feeder.

    · CW Make-up pumps (2no) & piping installed and commissioned.

    · DM Plant Feed Pumps(2no), temporarily installed in this pump house along with a PSF, commissioned.

    · AHP Seal Water Pumps (2no) installed and commissioned.


    5. DM Plant:

    DM Plant & Re-generation Bldg:

    · Major Civil, Electro-mechanical work completed.

    · Balance Plastering in slow progress. Other Finishing work not taken up.

    · Fixing of Doors/Rolling shutters/Window glasses pending.

    · Roof Treatment, fixing RWDC, Painting pending.

    · PLC panels are not commissioned yet.

    · Illumination pending.


    Neutralizing Pit & Drains:

    · Complete with Acid-Alkali Proof PVC Lining.

    · RCC work for Drains/trenches complete with Lining.

    · Civil work for Acid/Alkali Storage Tanks foundations & dyke is complete with Acid proof Flooring.

    De-Gasser Storage Area:

    · Tanks complete with Rubber lining.

    · Degasser Towers/Blowers erected.

    DM Water Storage area:

    · DM Storage Tanks (2no) are ready.

    · Erection of Pipe Rack completed.

    · DM Re-generation Pumps & DM Transfer Water Pumps installed and piping work completed.

    · Paving work not taken up yet.


    6. CW, ACW & FW Pump House & Electrical Bldg:

    · Major work completed, including RCC and Steel structures (Roof slab in progress).

    · Brickwork nearing completion.

    · Fixing Doors & Windows complete major complete for Electrical Bldg.

    · False Ceiling & Flooring in Control Room completed.

    · CW Pumps (3no) and ACW Pumps (2no) already commissioned.

    · Out of 2 sets, 1no Diesel Engine Fire Pump and 1no Jockey Pumps have been commissioned.

    · Installation of 2no Chain Pulley Block & Monorails pending for Screen/Gate lifting.

    · Illumination pending.


    7. Ash Handling Plant:

    Ash Slurry Pump House & Electrical Bldg

    Major Civil, Mechanical & Electrical work completed.

    Fixing Door/Window/Rolling Shutters partly remaining.

    Erection of EOT Crane pending.*

    AC & False Ceiling in PLC Room not yet provided.

    Illumination not provided.

    Ash Silos (2 no): Complete.

    Silo Utility & Electrical Bldg : Major Civil & Electrical work complete. Silo MCC panels & Silo Utility Panel charged.

    Vacuum Pump House & Electrical Bldg :

    Major Civil work completed except fixing Window Glasses and Glazed Partition work for PLC.

    Major Electro-Mechanical work completed except EOT crane erection*.

    ISH : Civil/structural work completed. Equipment already commissioned.

    Ash water Pipe Rack:

    Civil work/Structure Erection complete. Structural work strengthened for deflected Galleries.

    Ash Disposal Lines to Ash Pond :

    Major RCC Pedestals complete except in Ash Pond area.

    Civil work for Thrust Blocks major completed.

    *Rail Culvert (by Jack Pushing) not started.

    *2no Ash Disposal line made partly ready from Ash Slurry Pump to discharge the Ash to existing slurry lines outside the Plant premise.


    *Recovery Water Pump House : Civil work not started yet.

    *Clarifier & Chemical House (AHP) : Vendor not ordered by UCC. Drawings not available.


    8. Mill Reject System*

    Compressors (2no) installed. Air Receiver installed.

    Reject Silo Bin : Erection of Structures started in this month .


    9. Effluent Plant*

    Contractor started mobilization.

    Civil drawing is not available.


    10. Chlorination Plants(CW) : Civil work not started yet. Drawings are available.

    Chlorination Plants(RW) : Work not started.


    11. Permanent Store Bldg* : Civil work not started yet.

    12. RW Make-up system (by M/s. SPML)

    Intake Well Pump House :

    Major Civil work for Intake well & Pump House, Approach bridge, Sub-station etc completed.

    Pipelines till plant Valve room complete. Installation of all 5no Vertical Turbine Pumps and Header pipe completed. EOT crane erected. Dismantling of Cofferdam started.