Santaldih Thermal Power Station - WBPDCL

Would you like to react to this message? Create an account in a few clicks or log in to continue.
Santaldih Thermal Power Station - WBPDCL

This site is made for sharing information of STPS & on going projects at STPS - Unit#5 and Unit#6

Latest topics

» santhaldih tps web site
Progress/Program of M/s. BHEL for Major Balance Activities. Empty25th June 2013, 13:34 by rajena

» Progress Report of Unit No. 6 for the month of May 2009
Progress/Program of M/s. BHEL for Major Balance Activities. Empty19th June 2009, 14:15 by mbdcl

» Progress/Program of M/s. BHEL for Major Balance Activities.
Progress/Program of M/s. BHEL for Major Balance Activities. Empty27th April 2009, 14:35 by mbdcl

» Unit No.5 : Status of Pending BOP work.
Progress/Program of M/s. BHEL for Major Balance Activities. Empty27th April 2009, 14:15 by mbdcl

» Unit No.5 : Status of Pending BOP work.
Progress/Program of M/s. BHEL for Major Balance Activities. Empty27th April 2009, 14:14 by mbdcl

» Updated Status of Balance work on Main Plant package
Progress/Program of M/s. BHEL for Major Balance Activities. Empty13th March 2009, 18:00 by mbdcl

» Updated Status of Unit-5 Balance Work for BOP Package
Progress/Program of M/s. BHEL for Major Balance Activities. Empty12th March 2009, 19:12 by mbdcl

» Status Report of Unit No.6 Construction as on 12.03.09.
Progress/Program of M/s. BHEL for Major Balance Activities. Empty12th March 2009, 14:48 by mbdcl

» [b]Progress of Unit No.5 BOP Construction as on date 20.02.09.[/b]
Progress/Program of M/s. BHEL for Major Balance Activities. Empty9th February 2009, 18:03 by mbdcl


    Progress/Program of M/s. BHEL for Major Balance Activities.

    avatar
    mbdcl


    Posts : 9
    Join date : 2009-02-04

    Progress/Program of M/s. BHEL for Major Balance Activities. Empty Progress/Program of M/s. BHEL for Major Balance Activities.

    Post  mbdcl 27th April 2009, 14:35

    Sl NoMajor Activities Progress Program
    1 Ash Handling Plant (Ash Disposal lines to Ash pond) Ash Disposal Lines – Completed partly. October’09
    2Ash Recovery system Ash Recovery Pump house-not started. Clarifier, Chemical house & Misc Sumps-Ordering incomplete/Drgs not available.Dec’09
    3Mill Reject system Mechanical & piping work in progress 31.05.09
    4 Fire Hydrant & Detection system Incomplete 15.05.09
    5 Illumination Main Plant incomplete & BOP areas-almost nil 31.05.09
    6Delivery of Fire Tender Ordered this month 31.10.09
    7 Boiler LiftCivil work incomplete 07.06.09
    8Lifts in Power House, Technical Bldg & Mill Bldg Civilwork incomplete 30.10.09


    Last edited by mbdcl on 28th April 2009, 19:39; edited 1 time in total (Reason for editing : Updating)